New Construction • Final Inspection
THE HOME DEPOT
THE HOME DEPOT
Leander, Texas
📍 Commercial Roof Inspection Report — April 2026
104,000
SQ FT
TPO
60 MIL
12
RTU UNITS
📋 Report Summary
Overall Condition
EXCELLENT
Inspection Date
April 17, 2026
Report Date
April 17, 2026
Invoice #
APA-HD-0426
Weather
82°F / Clear / 15mph SE
Roof System Specifications
TPO SystemRoof TypeLow-Slope Commercial
MembraneTPO (White/Reflective)
ManufacturerCarlisle / GAF / Firestone
Thickness60 mil
AttachmentMechanically Fastened
Deck Type22ga Steel Deck
InsulationPolyisocyanurate (ISO)
Insulation Thickness4.5" (R-25.6)
Cover Board1/2" DensDeck Prime
Square Footage104,000 sq ft
System Notes: Fully adhered TPO system with hot-air welded seams. White reflective surface meets ENERGY STAR and CRRC requirements. 20-year manufacturer warranty available upon registration.
Drainage System
Fully FunctionalDrain ConditionClear, no debris
Ponding ObservedNone — proper slope maintained
Scupper ConditionUnobstructed, properly flashed
Drainage Assessment: All internal drains clear of construction debris. Positive drainage observed throughout roof field. No evidence of standing water or ponding exceeding 48 hours. Overflow scuppers properly located and sized per code.
Membrane Condition
Excellent — New Excellent — New installation, no visible defects
Good — Minor cosmetic imperfections
Fair — Some wear or weathering visible
Poor — Damage, punctures, or deterioration
Detailed Observations: Membrane is uniformly white with no signs of blistering, ridging, or shrinkage. No punctures, cuts, or impact damage observed. Surface is clean with minimal construction dust.
Additional notes: _________________________________
Seams & Heat Welds
Intact — Properly Welded Intact — All seams properly heat-welded, no fishmouths
Minor issues — Small gaps or incomplete welds
Major issues — Separation, failed welds, or open seams
Seam Inspection: Random sampling of seams confirms proper 1.5" heat welds with consistent bleed-out. No fishmouths, wrinkles, or voids. T-joints properly reinforced. Probe testing confirms watertight integrity.
Location of any concerns: _________________________
Flashings & Penetrations
Properly Sealed
Flashing Assessment: All penetrations properly flashed with prefabricated TPO boots or field-wrapped flashing. Parapet walls have TPO extended 8" under coping. No exposed fasteners or sealant failures.
Notes: _____________________________________
HVAC & Rooftop Equipment
12 Units — All DocumentedRTU #1-4 (Carrier)25-ton, curbs intact
RTU #5-8 (Trane)20-ton, curbs intact
RTU #9-12 (Lennox)15-ton, curbs intact
Exhaust Fans (6)Greenheck, operational
Condenser Units (2)Carrier, curbs intact
Kitchen Exhaust (1)CaptiveAire, properly flashed
Equipment Assessment: All 12 RTUs properly set on curbs with TPO flashing. No signs of water infiltration. Condensate lines routed to drains. Equipment screens secure. No refrigerant leaks or oil staining.
Notes: _____________________________________
Safety & Access
Partial Compliance
Safety Assessment: Roof access ladder and hatch secure. Walkway pads installed. Six fall protection anchors perimeter installed. Recommend posting OSHA signage. Guardrails not required (parapet exceeds 39").
Deficiencies: _______________________________
Thermal Imaging Analysis
No Anomalies DetectedCameraDJI Mavic 3T (640x512)
Emissivity Setting0.95 (TPO standard)
Date / TimeApril 17, 2026 / 10:30 AM
Ambient Temp82°F
Sky ConditionsClear, full sun
Scan Coverage100% of roof area
Thermal Findings — Full Roof Scan: Uniform thermal signature. No thermal bridging, wet insulation, or subsurface moisture. Delta-T consistent with dry ISO insulation. No anomalies at seams, flashings, or penetrations.
RTU & Penetration Scan: Equipment curbs and penetrations show proper thermal isolation. No air leakage at flashing terminations.
RTU & Penetration Scan: Equipment curbs and penetrations show proper thermal isolation. No air leakage at flashing terminations.
Complete Areas Inspected
100% Coverage
Areas Not Inspected (Limited Access):
None — full roof access achieved
Inspection Methodology: Visual inspection conducted via DJI Mavic 3T drone with 640x512 thermal sensor. All accessible areas documented with 48MP imagery and radiometric thermal data. Performed in accordance with ASTM E2270 and NRCA guidelines.
📸 Photo Gallery
Inspection Photo Gallery
High-resolution aerial documentation — The Home Depot, Leander, Texas
34
Total Images
48MP
Resolution
4:3
Aspect Ratio
Overview shots • Membrane details • Seam close-ups • Flashing documentation • RTU conditions • Thermal overlays
📸 View Photo Previews →📎 The FULL resolution photos will be delivered separately via email.
PRIORITY 1: IMMEDIATE (0-30 DAYS)
No immediate action — roof is new
Submit manufacturer warranty registration
Post OSHA signage at roof access
PRIORITY 2: 3-6 MONTHS
Schedule first maintenance inspection
Clean drains and gutters post-construction
Inspect all sealants after seasonal change
PRIORITY 3: ONGOING / ANNUAL
Bi-annual professional inspections
Document all maintenance for warranty
Restrict unauthorized roof access